Please note only the first sheet was updated for v8
Items updated in version 8:
Extended cable tray on Y-Arm to FCES beam tube enclosure
Updated PSL and ISC rack locations next to PSL enclosure
Updated pipe bridge cable tray/SQZ tables/SQZ racks
Updated CER Mezzanine VDD racks and cable tray layout
Added MER mezzanine racks and cable tray
Renaming of CER racks PEM/TCS/ISC/SQZ
Removal of table enclosure ISCHT6R
Removal of table enclosure IOHT2R
Updated CER cable tray layout
Updated SUS-R5 rack location
Updated TCS-R2 location
Removal of H2 racks
Added SUS-R7
Added ISC-R6
Added HAM7
For A+ installation details see LIGO-D2000371-v2 and LIGO-D2000372-v1